Estimate to finish up school job: Add $13B

State report on projects says prices can only rise
Friday, February 17, 2006 • BY DUNSTAN McNICHOL • Star-Ledger Staff

State taxpayers, who have already paid $6billion for a court-ordered overhaul of public schools in needy communities, would have to spend about $13billion more to finish the job, state officials say.

The Department of Education yesterday gave the Legislature its estimate of what it would cost to complete all 313 school construction and renovation projects awaiting work under a state Supreme Court mandate.

The department puts the tab at $12.8billion -- at today's prices. Figuring that the costs of everything from land to labor will keep going up, it projects the total would grow by about 7.5 percent each year the work is delayed, topping $29billion 10 years from now.

Lawmakers, facing a multibillion-dollar budget gap, a transportation fund gone bust and a severely underfunded pension system, reacted warily.

"These figures underscore why the Legislature needs to move cautiously before authorizing any further financing for a statewide school construction program," said Assembly Speaker Joseph Roberts (D-Camden).

Officials with the education department and the Schools Construction Corp., the agency set up to manage the building program, warned that the estimates are "very speculative." They said some of the construction plans are being updated, while some might turn out to be unnecessary.

"It's hard to take these numbers and suggest they should form the basis for really thinking about the exact amount of funding that is needed," said Barry Zubrow, recently appointed by Gov. Jon Corzine to head the SCC.

But David Sciarra, the attorney who has pressed the long-running Abbott vs. Burke school funding case before the Supreme Court, said the cost estimates give lawmakers enough information to act on a new source of funds.

Sciarra noted the report says it would take about $5.3billion to complete 96 school projects that were already in design when the first $6billion allocated to the program was tapped out last summer.

"The Legislature and governor now have all the information they need to act," said Sciarra. "These needs presented in today's report are urgent, are not going away, and require immediate funding. We must not let our children wait any longer for safe and adequate schools."

Roberts and Senate Education Committee Chairwoman Shirley Turner (D-Mercer) both called the new construction estimates "sobering."

"It will be difficult to provide a new wave of construction funding until efforts are undertaken to account for previous expenditures and stronger safeguards are put in place to ensure that future construction dollars are not wasted," Roberts said.

The program has been in near-suspension for about a year, since the SCC revealed it was running out of the $6billion it was given to build and fix schools in 31 needy districts.

The Star-Ledger reported last year that the first six schools built by the corporation cost 45 percent more than 19 schools built at the same time without state involvement. An investigation by the state inspector general found that mismanagement at the SCC had led to "waste, fraud and abuse of taxpayers dollars."

That prompted a series of reforms, but meanwhile the fund ran dry with hundreds of projects undone. Corzine has set up a special committee to review SCC operations, assess the projects awaiting state funding and report to him by March 15 with options for revamping the program.

A Republican lawmaker yesterday called for legal action to overturn the entire Abbott case and relieve the state of the obligation to pay for the school building.

"There are alternatives to the Supreme Court decision that must be explored -- including a legal challenge to the court's mandate," said Assemblywoman Charlotte Vandervalk (R-Bergen). "While I recognize the state's obligation to provide a quality education to all our children, I disagree vehemently with a court-mandated expenditure of billions of dollars as the only solution available to us."

Three other prominent Republican lawmakers called on Corzine to appoint a special prosecutor to investigate evidence of criminal mismanagement, waste and fraud in the schools program. Anthony Coley, a spokesman for Corzine, said that is not needed. "The wheels of reform are already in motion," he said.

Yesterday's tally was the first update since 2000, when lawmakers approved the statewide school construction program in response to the state Supreme Court's order. At that time, the 31 communities covered by the order submitted plans to build 200 new schools and refurbish 260 more at a cost of $7.3billion.

Six years later, the state has committed the entire $6billion the Legislature authorized, but will complete only 71 new schools and renovate another 67. The estimate in yesterday's report would represent a tripling of the original funding.

"It's a more accurate reflection, which we didn't get in 2000," said Sciarra. "What we're getting now, finally, is a realistic assessment of overall need."

Corzine's spokesman said the governor is reviewing the report while waiting for his committee to make recommendations for reform: "He looks forward to working with the Legislature to ensure the program delivers schools that meet the needs of our children at the best possible price."

The 313 schools included in the cost projection include 142 new schools or classroom additions, 49 major renovations and repairs to 117 more.


Dunstan McNichol covers state government issues. He may be reached at dmcnichol@starledger.com or (609) 989-0341.
© 2006 The Star-Ledger. Used by NJ.com with permission.

Return to Articles page