Projected costs soar for fixing needy schools

Total tab, once $6B, on its way toward $20B
Sunday, November 27, 2005 • BY DUNSTAN McNICHOL AND STEVE CHAMBERS • Star-Ledger Staff

New Jersey taxpayers today face a larger bill to rebuild schools in the state's poorest districts than they did five years and $6 billion ago.

A Star-Ledger review of proposals for further school construction in 11 of the state's Abbott districts shows a projected price tag of $6.5 billion. That means the requests from these 11 districts alone, including Newark, Jersey City and Camden, would cost more than the $6 billion allocated in 2000 for the entire 31-district program. The Schools Construction Corp. exhausted those funds with most projects incomplete or never begun.

The other Abbott communities, including Paterson and Elizabeth, have yet to file their proposals, so the new round is on track to approach $14 billion -- and "that's probably just the tip of the iceberg," said Assemblyman Joseph Malone (R-Burlington), a sponsor of the 2000 legislation allocating the $6 billion and one of the critics of the SCC, which has overseen the largest capital construction project in state history.

The entire tab for the court-ordered program could come to $20 billion.

"You've whetted the appetite of people, and they can't help themselves," Malone said of the funding requests.

The $6.537 billion in requests from those 11 districts comes on top of $2.55 billion already spent there, and it is likely to lead to more borrowing by the state. New Jersey borrowed all of the initial $6 billion, and taxpayers currently face $600 million annual payments through 2021.

Officials say new projections are soaring because they incorporate realistic construction and land-acquisition costs. Five years ago, officials didn't include the land costs and were directed by the state to assume average construction costs of $125 per square foot. The new plans are running above $210 per square foot and include estimates to acquire properties.

"It's better to work with the real numbers," said Assemblyman Craig Stanley (D-Essex), who is hoping to persuade lawmakers to authorize $2 billion for the fund-depleted school building program before the legislative session ends in January. "It's better to know exactly what you're getting into."

 

UNDER REVIEW

The districts' new plans are required every five years under the law that established the state's school building program. The outlines will give legislators and policymakers their first glimpse into the magnitude of the challenge as they wrestle plans to refinance and retool the SCC.

Although the plans were due to the Department of Education by October, only 12 of the 31 communities bankrolled by the state have submitted completed proposals. The Star-Ledger reviewed proposals from 10 of the 12 communities that have filed, plus Newark's new plan, though the city has yet to officially file with the state.

Officials at the Department of Education declined to discuss the plans because they are still under review.

Launched in response to a 1998 state Supreme Court order in the long-running Abbott vs. Burke lawsuit over public school funding in the state's poorest communities, the school construction program was designed to repair and rebuild 460 outmoded school buildings. But the state built just 71 schools and renovated 67 others with that first $6 billion.

In February, a Star-Ledger analysis showed the average cost for each of the first six schools built by the state was 45 percent more than for each of 19 schools erected by local officials over the same time. That report prompted the state inspector general to probe the SCC and find mismanagement and cost overruns. In the months since, the top two SCC officials have resigned.

Gov.-elect Jon Corzine said he plans to overhaul the SCC in short order after taking office in January.

"We view the SCC as a major area for reform and will be making some proposals at the beginning of the administration," said Andrew Poag, a spokesman for Corzine's transition office. "What's gone on up until this point is unacceptable."

Only three of the 11 new proposals reviewed by The Star-Ledger were for less money than requests in 2000.

In Neptune, which received $239 million from the first $6 billion in state funding, officials said they are essentially finished with construction. They have requested just $2 million more.

In Long Branch, which got four new schools, the new plan calls for $66 million -- about half the projected cost of the district's 2000 plan.

And Phillipsburg, which still wants $111 million, came in $2 million below its 2000 request.

Those are the exceptions.

In places like Camden, Trenton and Gloucester, the price tags doubled despite the massive state investments.

In Camden, officials want $895 million, despite already receiving $305 million.

In Trenton, where the state already has spent $342 million, the district estimates it needs $650 million more.

And there's Gloucester.

The district already has received twice the amount it requested five years ago -- $74 million vs. $33 million -- but wants an additional $71 million.

"None of this is surprising, given that the original 2000 estimates were based on cost figures that were unrealistically low even at that time," said David Sciarra, executive director of the Education Law Center, the agency that has pursued the Abbott litigation on behalf of students in the needy communities.

The largest request for additional funding came from Newark, the state's largest city and one of the districts struggling to get projects off the ground.

Since 2000, Newark has received $741 million of the $1.57 billion it requested. In its new plan, officials said the city needs an additional $3.2 billion -- more than the combined gross domestic product of Aruba and Greenland.


Dunstan McNichol may be reached at dmcnichol@starledger.com or (609) 989-0341. Steve Chambers may be reached at schambers@starledger.com or (973) 392-1674.
© 2005 The Star-Ledger. Used by NJ.com with permission.

Return to Articles page